Jertih ECRL station gets RM16m transit hub, works to start March 2027

Rummah EditorialRummah Editorial··2 min read

Terengganu will build a RM16 million transit terminal and access roads beside the East Coast Rail Link (ECRL) station in Jertih, Besut, with works due to start in March 2027 and run for 24 months, the state assembly heard on 16 November 2026.

State infrastructure, utilities and rural development committee chairman Datuk Hanafiah Mat said procurement would be held on 26 November and the letter of acceptance was expected to go out on 1 March 2027. He was answering Dr Riduan Mohamad Nor (PAS-Jertih) at the assembly's budget sitting at Wisma Darul Iman, Kuala Terengganu, Bernama reported through Kosmo. Sinar Harian carried the same figures.

The project, which the state calls a transit-oriented development (TOD), "is now at the stage of aligning project requirements and procurement preparation before entering the construction phase," Hanafiah said, speaking in Malay.

The scope covers site clearing, a transit terminal and access roads, along with a surau, a guard post, toilets, shops and rental kiosks, and a covered walkway from the station to the transport centre. Solar street lights, high-mast lamps, drainage and sewerage, slope protection and landscaping are also included.

The Public Works Department (JKR) Terengganu received the proposed scope from the Besut District Council, and is preparing the government's requirements document before the design is finalised, Hanafiah said. Several coordination meetings have been held with JKR, the state Economic Planning Unit and other agencies. He did not say how many shops or kiosks there will be, how they will be let, or who will run the terminal.

Jertih is one of six ECRL stations on the line's 242km run through Terengganu, alongside Chukai, Kemasik, Dungun, Kuala Terengganu and Bandar Permaisuri. The railway is scheduled to start carrying passengers in mid-December, with Gombak to Kuala Terengganu taking about three hours and Gombak to Kota Bharu about four, Bernama reported.

On the timetable Hanafiah gave, the terminal would be finished around March 2029, more than two years after the first trains stop at Jertih.

Sources: Kosmo (Bernama), Sinar Harian.