Malaysia's rail lines, and the ones on the way
22 lines run today. 8 more are being built or planned, from the East Coast Rail Link to the RTS Link into Singapore. Play the timeline to watch the network fill in, year by year.
Play the timeline on the interactive mapEvery line, running and planned, with a slider from today to 2032. Turn on data centres, investment zones or home prices alongside.Open the mapOpening next
- ECRL Phase 1 (Kota Bharu - ITT Gombak)Under construction, due Dec 2026520 km
- Johor Bahru - Singapore RTS LinkUnder construction, due Feb 20274.6 km
- ECRL freight spurs (Kuantan Port, Kemaman, Kerteh, Port Klang)Under construction, due 202826.9 km
- ECRL Phase 2 (Gombak junction - Serendah - Port Klang)Under construction, due Jan 202874.4 km
- Penang LRT Mutiara Line (Silicon Island - Komtar)Under construction, due Dec 203127 km
- Mutiara Line extension (Komtar - Penang Sentral, sea crossing)Planned, due Dec 20316 km
- MRT3 Circle LinePlanned, due 203254.1 km
- Sabah State Railway Tenom - Melalap section (rebuild)Proposed, due 203213.9 km
Milestones, in order
2025
MRT3 Circle Line: Final approval by the Transport Ministry
lowyat.netJan 2025
KL - Singapore HSR: Evaluation of 7 consortium concept proposals (RFI) presented to Cabinet
paultan.orgDec 2025
KTM Gemas-JB electrified double track: Line launched by the Regent of Johor (192 km, 11 stations), completing electrified double track KL-JB
malaymail.comDec 2025
KTM Gemas-JB electrified double track: ETS3 KL Sentral - JB Sentral passenger service starts
malaymail.com2026, not confirmed
MRT3 Circle Line: Construction tenders restart (analyst expectation)
edgeprop.myFeb 2026
Penang LRT Mutiara Line: Revised scheme with Komtar - Penang Sentral sea crossing on public inspection (to 24 May 2026)
malaymail.comJun 2026
Penang LRT Mutiara Line: Overall works progress 8.99%
paultan.orgJun 2026
LRT3 Shah Alam Line: Officially launched by the Prime Minister at Johan Setia depot
paultan.orgJun 2026
LRT3 Shah Alam Line: Opens to the public: Bandar Utama - Johan Setia, 37.8 km, 20 stations
ringgitplus.comAug 2026
ECRL: Phase 1 works 95.08% complete, in testing and commissioning
nst.com.myAug 2026
Penang LRT Mutiara Line: RM3.03bn systems turnkey contract awarded to MRCB - Theta Edge JV
bernama.comOct 2026
RTS Link: Transport Minister: no delay; station and CIQ physical works complete; February leaves a buffer for safety approvals
malaymail.comOct 2026
ECRL: Cabinet approves dynamic fares (Gombak - Kota Bharu economy from RM125)
bernama.comOct 2026, target
ECRL: Fault-free running tests begin, Kota Bharu - Gombak
bernama.comNov 2026, target
ECRL: Ticket sales open
bernama.comNov 2026, target
ECRL: Trial operations
bernama.comNov 2026, target
Penang LRT Mutiara Line: Contract award for the Komtar - Penang Sentral extension
bernama.comDec 2026, not confirmed
Kuching ART (Sarawak Metro): Blue Line first-phase operations
en.wikipedia.orgDec 2026, target
LRT3 Shah Alam Line: Construction of the five provisional stations to start
paultan.orgDec 2026, target
MRT3 Circle Line: Land acquisition completed
lowyat.netDec 2026, target
ECRL: Phase 1 passenger service Kota Bharu - ITT Gombak begins
bernama.comDec 2026, target
RTS Link: Final system tests and trial runs complete (operator RTSO)
lta.gov.sg2027, target
MRT3 Circle Line: Physical construction begins
mrt.com.my2027, target
Penang LRT Mutiara Line: Site entry for segment 2 (Macallum - Penang Sentral)
bernama.comJan 2027, target
ECRL: Phase 1 passenger service: official schedule
nst.com.myFeb 2027, target
RTS Link: Passenger service starts: Bukit Chagar (JB) - Woodlands North (SG), about 5 minutes
lta.gov.sgAug 2027, target
KTM Shuttle Tebrau: KTMB services into Singapore to end within six months of RTS Link passenger start
mot.gov.sgDec 2027, target
ECRL: Phase 2 (Gombak - Serendah - Port Klang) completed
theedgemalaysia.comJan 2028, target
ECRL: Cargo operations and Phase 2 services begin
nst.com.myDec 2031, target
Penang LRT Mutiara Line: Passenger operations begin
paultan.org2032, target
MRT3 Circle Line: Operations: 51 km loop, 32 stations incl. 3 provisional
mrt.com.my
Every line
| Line | Type | Status | Length | Stations | Operator |
|---|---|---|---|---|---|
| LRT Ampang Line | LRT | Opened Dec 1996 | 14.9 km | 18 | Rapid Rail (Prasarana) |
| LRT Sri Petaling Line | LRT | Opened Jul 1998 | 37.3 km | 29 | Rapid Rail (Prasarana) |
| LRT Kelana Jaya Line | LRT | Opened Sept 1998 | 45.6 km | 37 | Rapid Rail (Prasarana) |
| KL Monorail Line | Monorail | Opened Aug 2003 | 8.6 km | 11 | Rapid Rail (Prasarana) |
| MRT Kajang Line | MRT | Opened Dec 2016 | 51.3 km | 30 | Rapid Rail (Prasarana) |
| LRT Shah Alam Line | LRT | Opened Jun 2026 | 37.4 km | 26 | Rapid Rail (Prasarana) |
| MRT Putrajaya Line | MRT | Opened Jun 2022 | 56.9 km | 41 | Rapid Rail (Prasarana) |
| BRT Sunway Line | BRT | Opened Jun 2015 | 5.1 km | 7 | Rapid Rail (Prasarana) |
| KTM Komuter Seremban Line | KTM Komuter | Opened 1995 | 120.9 km | 27 | Keretapi Tanah Melayu (KTMB) |
| KTM Komuter Port Klang Line | KTM Komuter | Opened 1995 | 118.8 km | 34 | Keretapi Tanah Melayu (KTMB) |
| KTM Komuter Utara Padang Besar Line | KTM Komuter | Opened 2015 | 161.5 km | 13 | Keretapi Tanah Melayu (KTMB) |
| KTM Komuter Utara Ipoh Line | KTM Komuter | Running | 145.2 km | 13 | Keretapi Tanah Melayu (KTMB) |
| KTM Komuter Shuttle Selatan | KTM Komuter | Running | 127.6 km | 9 | Keretapi Tanah Melayu (KTMB) |
| KTM ETS (Electric Train Service) | ETS | Opened Aug 2010 | 821.2 km | 49 | Keretapi Tanah Melayu (KTMB) |
| KTM Intercity Shuttle Timuran (East Coast Line) | Intercity | Running | 488.7 km | 55 | Keretapi Tanah Melayu (KTMB) |
| KTM Intercity Ekspres Rakyat Timuran | Intercity | Running | 631.5 km | 24 | Keretapi Tanah Melayu (KTMB) |
| KTM Shuttle Tebrau (JB Sentral - Woodlands) | Intercity | Running | 2.2 km | 2 | Keretapi Tanah Melayu (KTMB) |
| ECRL Phase 1 (Kota Bharu - ITT Gombak) | ECRL | Due Dec 2026 | 520 km | 16 | Malaysia Rail Link (MRL); built by CCCC |
| ECRL Phase 2 (Gombak junction - Serendah - Port Klang) | ECRL | Due Jan 2028 | 74.4 km | 3 | Malaysia Rail Link (MRL); built by CCCC |
| ECRL freight spurs (Kuantan Port, Kemaman, Kerteh, Port Klang) | ECRL | Due 2028 | 26.9 km | Malaysia Rail Link (MRL) | |
| Johor Bahru - Singapore RTS Link | Cross-border shuttle | Due Feb 2027 | 4.6 km | 2 | RTS Operations Pte Ltd (Prasarana-SMRT JV) |
| MRT3 Circle Line | MRT | Due 2032 | 54.1 km | 32 | MRT Corp |
| Penang LRT Mutiara Line (Silicon Island - Komtar) | LRT | Due Dec 2031 | 27 km | 20 | MRT Corp (owner); Penang state is project partner |
| Mutiara Line extension (Komtar - Penang Sentral, sea crossing) | LRT | Due Dec 2031 | 6 km | 2 | MRT Corp |
| KLIA Ekspres (Express Rail Link) | Airport rail | Opened Apr 2002 | 58.9 km | 3 | Express Rail Link Sdn Bhd (ERL) |
| KLIA Transit (Express Rail Link) | Airport rail | Opened Jun 2002 | 58.9 km | 6 | Express Rail Link Sdn Bhd (ERL) |
| Sabah State Railway (Tanjung Aru - Tenom) | Intercity | Opened 1896 | 135.9 km | 16 | Sabah State Railway Department (JKNS) |
| Sabah State Railway Tenom - Melalap section (rebuild) | Intercity | Due 2032 | 13.9 km | Sabah State Railway Department | |
| Penang Hill Railway (funicular) | Rail | Opened Oct 1923 | 2 km | 4 | Penang Hill Corporation |
| KTM Gemas - Johor Bahru electrified double track | ETS | Opened Dec 2025 | 193.3 km | 1 | Keretapi Tanah Melayu (KTMB) |
Sources
Lines running today come from the official timetables (GTFS) published on data.gov.my under CC BY 4.0. KTM lines are drawn station to station because that feed has no route shapes. Lines under construction come from OpenStreetMap (© OpenStreetMap contributors, ODbL).
Dates come from the Transport Ministry, the operators and reports linked beside each milestone. A target is a target: it can slip.
Download
The milestone list, with a source for every date.
Download CSVQuestions
- When does the RTS Link open?
- Passenger service between Bukit Chagar in Johor Bahru and Woodlands North in Singapore is targeted for February 2027, according to a joint statement by Singapore’s Land Transport Authority and Malaysia’s Transport Ministry on 2 October 2026. Trial runs are due to finish by 31 December 2026.
- When will the ECRL start running?
- Phase 1 between Kota Bharu and ITT Gombak is targeted to carry passengers from 12 December 2026, subject to safety approval; the official schedule says January 2027. Phase 2 to Port Klang and cargo services follow in 2027 and 2028.
- When will the Penang LRT open?
- The Mutiara Line from Silicon Island to Komtar is due to start passenger operations in December 2031. Works were 8.99% complete in June 2026.
- When will MRT3 open?
- The MRT3 Circle Line, a 51 km loop around Kuala Lumpur with 32 stations, is due to open in 2032, with physical construction starting in 2027. Its stations on this map are placed approximately until the alignment is published.
- Is the KL-Singapore high-speed rail on the map?
- No. There is no approved alignment or decision yet, so it is not drawn. It will be added if one is announced.
See the lines with data centres, investment zones and home prices on the Explore Malaysia map, or ride Penang's future LRT in 3D.