Malaysia's rail lines, and the ones on the way

22 lines run today. 8 more are being built or planned, from the East Coast Rail Link to the RTS Link into Singapore. Play the timeline to watch the network fill in, year by year.

Play the timeline on the interactive mapEvery line, running and planned, with a slider from today to 2032. Turn on data centres, investment zones or home prices alongside.Open the map

Opening next

Milestones, in order

  1. 2025

    MRT3 Circle Line: Final approval by the Transport Ministry

    lowyat.net
  2. Jan 2025

    KL - Singapore HSR: Evaluation of 7 consortium concept proposals (RFI) presented to Cabinet

    paultan.org
  3. Dec 2025

    KTM Gemas-JB electrified double track: Line launched by the Regent of Johor (192 km, 11 stations), completing electrified double track KL-JB

    malaymail.com
  4. Dec 2025

    KTM Gemas-JB electrified double track: ETS3 KL Sentral - JB Sentral passenger service starts

    malaymail.com
  5. 2026, not confirmed

    MRT3 Circle Line: Construction tenders restart (analyst expectation)

    edgeprop.my
  6. Feb 2026

    Penang LRT Mutiara Line: Revised scheme with Komtar - Penang Sentral sea crossing on public inspection (to 24 May 2026)

    malaymail.com
  7. Jun 2026

    Penang LRT Mutiara Line: Overall works progress 8.99%

    paultan.org
  8. Jun 2026

    LRT3 Shah Alam Line: Officially launched by the Prime Minister at Johan Setia depot

    paultan.org
  9. Jun 2026

    LRT3 Shah Alam Line: Opens to the public: Bandar Utama - Johan Setia, 37.8 km, 20 stations

    ringgitplus.com
  10. Aug 2026

    ECRL: Phase 1 works 95.08% complete, in testing and commissioning

    nst.com.my
  11. Aug 2026

    Penang LRT Mutiara Line: RM3.03bn systems turnkey contract awarded to MRCB - Theta Edge JV

    bernama.com
  12. Oct 2026

    RTS Link: Transport Minister: no delay; station and CIQ physical works complete; February leaves a buffer for safety approvals

    malaymail.com
  13. Oct 2026

    ECRL: Cabinet approves dynamic fares (Gombak - Kota Bharu economy from RM125)

    bernama.com
  14. Oct 2026, target

    ECRL: Fault-free running tests begin, Kota Bharu - Gombak

    bernama.com
  15. Nov 2026, target

    ECRL: Ticket sales open

    bernama.com
  16. Nov 2026, target

    ECRL: Trial operations

    bernama.com
  17. Nov 2026, target

    Penang LRT Mutiara Line: Contract award for the Komtar - Penang Sentral extension

    bernama.com
  18. Dec 2026, not confirmed

    Kuching ART (Sarawak Metro): Blue Line first-phase operations

    en.wikipedia.org
  19. Dec 2026, target

    LRT3 Shah Alam Line: Construction of the five provisional stations to start

    paultan.org
  20. Dec 2026, target

    MRT3 Circle Line: Land acquisition completed

    lowyat.net
  21. Dec 2026, target

    ECRL: Phase 1 passenger service Kota Bharu - ITT Gombak begins

    bernama.com
  22. Dec 2026, target

    RTS Link: Final system tests and trial runs complete (operator RTSO)

    lta.gov.sg
  23. 2027, target

    MRT3 Circle Line: Physical construction begins

    mrt.com.my
  24. 2027, target

    Penang LRT Mutiara Line: Site entry for segment 2 (Macallum - Penang Sentral)

    bernama.com
  25. Jan 2027, target

    ECRL: Phase 1 passenger service: official schedule

    nst.com.my
  26. Feb 2027, target

    RTS Link: Passenger service starts: Bukit Chagar (JB) - Woodlands North (SG), about 5 minutes

    lta.gov.sg
  27. Aug 2027, target

    KTM Shuttle Tebrau: KTMB services into Singapore to end within six months of RTS Link passenger start

    mot.gov.sg
  28. Dec 2027, target

    ECRL: Phase 2 (Gombak - Serendah - Port Klang) completed

    theedgemalaysia.com
  29. Jan 2028, target

    ECRL: Cargo operations and Phase 2 services begin

    nst.com.my
  30. Dec 2031, target

    Penang LRT Mutiara Line: Passenger operations begin

    paultan.org
  31. 2032, target

    MRT3 Circle Line: Operations: 51 km loop, 32 stations incl. 3 provisional

    mrt.com.my

Every line

LineTypeStatusLengthStationsOperator
LRT Ampang LineLRTOpened Dec 199614.9 km18Rapid Rail (Prasarana)
LRT Sri Petaling LineLRTOpened Jul 199837.3 km29Rapid Rail (Prasarana)
LRT Kelana Jaya LineLRTOpened Sept 199845.6 km37Rapid Rail (Prasarana)
KL Monorail LineMonorailOpened Aug 20038.6 km11Rapid Rail (Prasarana)
MRT Kajang LineMRTOpened Dec 201651.3 km30Rapid Rail (Prasarana)
LRT Shah Alam LineLRTOpened Jun 202637.4 km26Rapid Rail (Prasarana)
MRT Putrajaya LineMRTOpened Jun 202256.9 km41Rapid Rail (Prasarana)
BRT Sunway LineBRTOpened Jun 20155.1 km7Rapid Rail (Prasarana)
KTM Komuter Seremban LineKTM KomuterOpened 1995120.9 km27Keretapi Tanah Melayu (KTMB)
KTM Komuter Port Klang LineKTM KomuterOpened 1995118.8 km34Keretapi Tanah Melayu (KTMB)
KTM Komuter Utara Padang Besar LineKTM KomuterOpened 2015161.5 km13Keretapi Tanah Melayu (KTMB)
KTM Komuter Utara Ipoh LineKTM KomuterRunning145.2 km13Keretapi Tanah Melayu (KTMB)
KTM Komuter Shuttle SelatanKTM KomuterRunning127.6 km9Keretapi Tanah Melayu (KTMB)
KTM ETS (Electric Train Service)ETSOpened Aug 2010821.2 km49Keretapi Tanah Melayu (KTMB)
KTM Intercity Shuttle Timuran (East Coast Line)IntercityRunning488.7 km55Keretapi Tanah Melayu (KTMB)
KTM Intercity Ekspres Rakyat TimuranIntercityRunning631.5 km24Keretapi Tanah Melayu (KTMB)
KTM Shuttle Tebrau (JB Sentral - Woodlands)IntercityRunning2.2 km2Keretapi Tanah Melayu (KTMB)
ECRL Phase 1 (Kota Bharu - ITT Gombak)ECRLDue Dec 2026520 km16Malaysia Rail Link (MRL); built by CCCC
ECRL Phase 2 (Gombak junction - Serendah - Port Klang)ECRLDue Jan 202874.4 km3Malaysia Rail Link (MRL); built by CCCC
ECRL freight spurs (Kuantan Port, Kemaman, Kerteh, Port Klang)ECRLDue 202826.9 kmMalaysia Rail Link (MRL)
Johor Bahru - Singapore RTS LinkCross-border shuttleDue Feb 20274.6 km2RTS Operations Pte Ltd (Prasarana-SMRT JV)
MRT3 Circle LineMRTDue 203254.1 km32MRT Corp
Penang LRT Mutiara Line (Silicon Island - Komtar)LRTDue Dec 203127 km20MRT Corp (owner); Penang state is project partner
Mutiara Line extension (Komtar - Penang Sentral, sea crossing)LRTDue Dec 20316 km2MRT Corp
KLIA Ekspres (Express Rail Link)Airport railOpened Apr 200258.9 km3Express Rail Link Sdn Bhd (ERL)
KLIA Transit (Express Rail Link)Airport railOpened Jun 200258.9 km6Express Rail Link Sdn Bhd (ERL)
Sabah State Railway (Tanjung Aru - Tenom)IntercityOpened 1896135.9 km16Sabah State Railway Department (JKNS)
Sabah State Railway Tenom - Melalap section (rebuild)IntercityDue 203213.9 kmSabah State Railway Department
Penang Hill Railway (funicular)RailOpened Oct 19232 km4Penang Hill Corporation
KTM Gemas - Johor Bahru electrified double trackETSOpened Dec 2025193.3 km1Keretapi Tanah Melayu (KTMB)

Sources

Lines running today come from the official timetables (GTFS) published on data.gov.my under CC BY 4.0. KTM lines are drawn station to station because that feed has no route shapes. Lines under construction come from OpenStreetMap (© OpenStreetMap contributors, ODbL).

Dates come from the Transport Ministry, the operators and reports linked beside each milestone. A target is a target: it can slip.

Download

The milestone list, with a source for every date.

Download CSV

Questions

When does the RTS Link open?
Passenger service between Bukit Chagar in Johor Bahru and Woodlands North in Singapore is targeted for February 2027, according to a joint statement by Singapore’s Land Transport Authority and Malaysia’s Transport Ministry on 2 October 2026. Trial runs are due to finish by 31 December 2026.
When will the ECRL start running?
Phase 1 between Kota Bharu and ITT Gombak is targeted to carry passengers from 12 December 2026, subject to safety approval; the official schedule says January 2027. Phase 2 to Port Klang and cargo services follow in 2027 and 2028.
When will the Penang LRT open?
The Mutiara Line from Silicon Island to Komtar is due to start passenger operations in December 2031. Works were 8.99% complete in June 2026.
When will MRT3 open?
The MRT3 Circle Line, a 51 km loop around Kuala Lumpur with 32 stations, is due to open in 2032, with physical construction starting in 2027. Its stations on this map are placed approximately until the alignment is published.
Is the KL-Singapore high-speed rail on the map?
No. There is no approved alignment or decision yet, so it is not drawn. It will be added if one is announced.

See the lines with data centres, investment zones and home prices on the Explore Malaysia map, or ride Penang's future LRT in 3D.